In October 2022, the final concrete hanbar was cast for Ōpōtiki’s new $100million harbour entrance. These hanbars surround and protect the 400m long seawalls being built to provide year-round river access to Ōpōtiki town and wharf. Hanbars are heavy concrete structures which protect the harbour’s rock core from sea erosion.
Director of Eastern Bay Concrete, Shane Clark, said that the first hanbar was cast back in October 2020 and around 12,000 hanbars had been cast with his company’s concrete since then. He said that the last couple of years have been very busy for his company and team as they scaled up to deliver concrete to HEB Construction [Lead contractor on the Ōpōtiki harbour design and build] for the seawalls.
“At our peak, we were supplying 90m3 (about 20 truck-loads) of specialty concrete to HEB Construction each day to be formed into these large hanbars.
“We met the strictest quality standards for our product because the hanbars are designed to stand the test of time in a complex marine environment. HEB set very high standards for quality and volume of product and we were able to meet those demands.
“Eastern Bay Concrete upscaled significantly to meet the production requirements on a project the size of the Ōpōtiki Harbour entrance. The support we had from Government was instrumental in this growth. We grew from a small team of 8, up to 19 people when we were at full production. We installed a new concrete plant, taking production capability from 20m3/hour to 60m3/hr and purchased four additional concrete trucks to meet the requirements of this project and other large projects that are set to start over the next few years.
“This illustrates that smaller business like ours are willing and able to grow their infrastructure and local workforce to take on these large contracts. We are well-placed to meet the coming demand as other large projects come online across the region,” Mr Clark said.
Mr Clark also emphasised the importance of local businesses doing as much of the work as possible on large-scale infrastructure projects due to maximise long-term benefits for the local community. This local workforce focus was built into the contacts from the very start of the Ōpōtiki Harbour project and continues through all stages.
“As a company we have gained a lot of new expertise and experience through the harbour development project. We take a lot of pride in our role in the development of the aquaculture industry here in the Eastern Bay of Plenty. The enthusiasm, hard work and dedication of my team at Eastern Bay Concrete has been second to none. Our team, who are all locals, see this growth in Ōpōtiki’s infrastructure as a direct benefit to them and their families, now and into the future,” Mr Clark said.
Ends
Hanbar concrete reinforcing units range in size from 2-tonne (1.2m tall) to 15 tonnes (2.4m tall). The moulds were constructed using local company C Hayes Engineering.